Construction Updates

In early November 2025, site readiness work for the BPCR Project began. Site readiness work are the initial activities carried out on a project site to prepare the site for the main project construction. Activities will include utility relocation, underground assessments, installation of subsurface tide gate infrastructure, and other necessary work to help create the conditions needed for full-scale construction to begin safely in 2026. Site readiness work will ramp up in intensity & duration as the start of project construction approaches.

Stay informed by signing up for our
construction newsletter.

Construction Timeline

Estimated Start Dates and Durations of Upcoming N/WBCPR Resiliency Work:

  • ​West St Crossing: 3rd Quarter 2026 (48 months) 

  • North Esplanade: 3rd Quarter 2026 (43 months) 

  • Rockefeller Park: 2nd Quarter 2028 (28 months) 

  • Belvedere Plaza: 1st Quarter 2027 (43 months) 

  • North Cove: 1st Quarter 2026 (57 months) 

  • South Esplanade: 1st Quarter 2026 (51 months) 

  • South Cove: 1st Quarter 2026 (28 months)

​

Construction is anticipated to begin in late 2025 and finish in late 2030. This timeline is dependent on agency approvals and construction logistics and is subject to modifications. We will keep the community informed as plans progress.  

​

Learn more about each area below!

View the scheduled timeline of the Project.

View a flythrough of the Project's design.

West St Crossing / Tribeca
BPCR_ConstructionReach-WestStreetCross (1).png

Estimated construction duration for West St Crossing / Tribeca is 48 months, starting 3rd Quarter 2026.​

​

What to expect:

  • Flood Barrier System (FBS) Alignment: Starting at Greenwich Street, west along North Moore Street and south along West Street / Route 9A, crossing to Stuyvesant Plaza.

  • Located adjacent to, Independence Plaza, Borough of Manhattan Community College (BMCC), Stuyvesant Plaza.

  • Anticipated construction impacts include noise, visual changes to the area due to construction activity, and restricted access to some open spaces.

  • Working hours are 7:00 AM – 6:00 PM, Monday through Friday.

​

Current conditions:

  • Site readiness work is underway in Stuyvesant Plaza. Teams are conducting survey work in this area ahead of construction activity in the coming weeks.

  • Construction barriers and fencing with noise dampening blankets will be erected. Crews will put up protective barriers for planters in this area. Some trees and planters will be removed to clear the site ongoing construction activity.

  • A test pit will be created to locate a water line in the site area. Maintenance work to repair and resurface asphalt will take place.

  • There will also be work to relocate decorative pavers present in Stuyvesant Plaza to another location in the neighborhood.