
Construction Updates
In early November 2025, site readiness work for the BPCR Project began. Site readiness work is the initial activities carried out on a project site to prepare the site for the main project construction. Activities will include utility relocation, underground assessments, installation of subsurface tide gate infrastructure, and other necessary work to help create the conditions needed for full-scale construction to begin safely in 2026. Site readiness work will ramp up in intensity & duration as the start of project construction approaches.
Stay informed by signing up for our construction newsletter.
Construction Timeline
Start Dates and Durations of Upcoming N/WBCPR Resiliency Work:
-
West St Crossing/Tribeca: 3rd Quarter 2026 (43 months)
-
North Esplanade: 3rd Quarter 2026 (43 months)
-
Rockefeller Park: 2nd Quarter 2028 (28 months)
-
Belvedere Plaza: 1st Quarter 2027 (43 months)
-
North Cove: 2nd Quarter 2026 (57 months)
-
South Esplanade: Spring 2026 (50 months)
-
South Cove: Commenced March 2026, ongoing through Spring 2028
Construction began in late 2025 and is scheduled to finish in late 2030. This timeline is dependent on agency approvals and construction logistics and is subject to modifications. We will keep the community informed as plans progress.
View a flythrough of the Project's design.
Project Areas
West St Crossing / Tribeca
.png)
Estimated construction duration for West St Crossing / Tribeca is 48 months, starting 3rd Quarter 2026.
What to expect:
-
Flood Barrier System (FBS) Alignment: Starting at Greenwich Street, west along North Moore Street and south along West Street / Route 9A, crossing to Stuyvesant Plaza.
-
Located adjacent to, Independence Plaza, Borough of Manhattan Community College (BMCC), Stuyvesant Plaza.
-
Anticipated construction impacts include noise, visual changes to the area due to construction activity, and restricted access to some open spaces.
-
Working hours are 7:00 AM – 6:00 PM, Monday through Friday.
Current conditions (Stuyvesant Plaza):
-
Fencing with noise dampening blankets and construction signage are present.
-
Crews continue to conduct nighttime work on the southbound lane of Route 9A, closest to Stuyvesant Plaza, including the relocation of underground utilities beneath the street.
West St Crossing / Tribeca Renderings























.png)







